Dept. of Trans. PROGRESS Serial No. Contract No. 10-021-12-51 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 40% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 01-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,025,809.38 10,192.90 2.a. Extra Work 489,111.32 164,181.46 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 0.00 -92,466.52 4. Earned Subject to Retention 12,936,525.65 81,907.84 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,236,525.65 7. Deductions -5,000.00 10,000.00 8. a.Contract Retentions -646,826.28 -4,095.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,584,699.37 87,812.45 10. Reduction Amt to Escrow 11. Payment to Escrow 646,820.00 12. Net Pymt. this Estimate 87,812.45