Dept. of Trans. PROGRESS Serial No. Contract No. 10-053-08-45 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 41% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 12 Payment period ending: 02-22-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,058,233.56 32,424.18 2.a. Extra Work 618,162.26 129,050.94 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 92,466.52 92,466.52 4. Earned Subject to Retention 13,190,467.29 253,941.64 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,398,000.77 7. Deductions 0.00 5,000.00 8. a.Contract Retentions -659,523.36 -12,697.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,830,943.93 246,244.56 10. Reduction Amt to Escrow 11. Payment to Escrow 659,520.00 12. Net Pymt. this Estimate 246,244.56