Dept. of Trans. PROGRESS Serial No. Contract No. 10-081-15-30 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 41% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 13 Payment period ending: 03-22-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,058,233.56 0.00 2.a. Extra Work 736,903.89 118,741.63 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 92,466.52 0.00 4. Earned Subject to Retention 13,309,208.92 118,741.63 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,516,742.40 7. Deductions 8. a.Contract Retentions -665,460.45 -5,937.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,943,748.47 112,804.54 10. Reduction Amt to Escrow 11. Payment to Escrow 665,460.00 12. Net Pymt. this Estimate 112,804.54