Dept. of Trans. PROGRESS Serial No. Contract No. 10-112-09-38 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 42% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 14 Payment period ending: 04-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,073,883.56 15,650.00 2.a. Extra Work 772,330.37 35,426.48 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 92,466.52 0.00 4. Earned Subject to Retention 13,360,285.40 51,076.48 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,567,818.88 7. Deductions 8. a.Contract Retentions -668,014.27 -2,553.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,992,271.13 48,522.66 10. Reduction Amt to Escrow 11. Payment to Escrow 668,010.00 12. Net Pymt. this Estimate 48,522.66