Dept. of Trans. PROGRESS Serial No. Contract No. 10-144-15-08 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 36% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 15 Payment period ending: 05-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,146,747.69 72,864.13 2.a. Extra Work 783,437.41 11,107.04 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 92,466.52 0.00 4. Earned Subject to Retention 13,444,256.57 83,971.17 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,651,790.05 7. Deductions 8. a.Contract Retentions -672,212.83 -4,198.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,072,043.74 79,772.61 10. Reduction Amt to Escrow 11. Payment to Escrow 672,210.00 12. Net Pymt. this Estimate 79,772.61