Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-15-39 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 50% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 18 Payment period ending: 08-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,075,932.91 1,312,175.47 2.a. Extra Work 904,780.81 61,828.35 b. Adjustment Comp. -578,395.05 0.00 3. Materials on Hand 52,348.64 -40,117.88 4. Earned Subject to Retention 15,454,667.31 1,333,885.94 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 17,702,318.67 7. Deductions 8. a.Contract Retentions -772,733.37 -66,694.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,981,933.94 1,267,191.64 10. Reduction Amt to Escrow 11. Payment to Escrow 772,730.00 12. Net Pymt. this Estimate 1,267,191.64