Dept. of Trans. PROGRESS Serial No. Contract No. 10-264-11-22 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 55% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 19 Payment period ending: 09-16-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,377,153.48 1,301,220.57 2.a. Extra Work 904,780.81 0.00 b. Adjustment Comp. -455,395.05 123,000.00 3. Materials on Hand 0.00 -52,348.64 4. Earned Subject to Retention 16,826,539.24 1,371,871.93 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 19,126,539.24 7. Deductions 8. a.Contract Retentions -841,326.96 -68,593.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,285,212.28 1,303,278.34 10. Reduction Amt to Escrow 11. Payment to Escrow 841,320.00 12. Net Pymt. this Estimate 1,303,278.34