Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-11-21 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 60% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 20 Payment period ending: 10-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,863,011.22 1,485,857.74 2.a. Extra Work 921,871.89 17,091.08 b. Adjustment Comp. -455,395.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,329,488.06 1,502,948.82 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 20,629,488.06 7. Deductions 8. a.Contract Retentions -916,474.40 -75,147.44 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,713,013.66 1,427,801.38 10. Reduction Amt to Escrow 11. Payment to Escrow 916,470.00 12. Net Pymt. this Estimate 1,427,801.38