Dept. of Trans. PROGRESS Serial No. Contract No. 10-326-10-16 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 64% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 21 Payment period ending: 11-19-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,370,803.56 507,792.34 2.a. Extra Work 949,210.88 27,338.99 b. Adjustment Comp. -455,395.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,864,619.39 535,131.33 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 21,164,619.39 7. Deductions 8. a.Contract Retentions -943,230.97 -26,756.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,221,388.42 508,374.76 10. Reduction Amt to Escrow 11. Payment to Escrow 943,230.00 12. Net Pymt. this Estimate 508,374.76