Dept. of Trans. PROGRESS Serial No. Contract No. 10-354-11-58 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 61% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 22 Payment period ending: 12-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,456,456.17 85,652.61 2.a. Extra Work 1,004,950.65 55,739.77 b. Adjustment Comp. -429,787.32 25,607.73 3. Materials on Hand 4. Earned Subject to Retention 19,031,619.50 167,000.11 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 21,331,619.50 7. Deductions 8. a.Contract Retentions -951,580.98 -8,350.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,380,038.52 158,650.10 10. Reduction Amt to Escrow 11. Payment to Escrow 951,580.00 12. Net Pymt. this Estimate 158,650.10