Dept. of Trans. PROGRESS Serial No. Contract No. 11-055-10-10 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 72% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 24 Payment period ending: 02-18-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,104,108.51 1,009,089.28 2.a. Extra Work 1,794,648.38 191,770.22 b. Adjustment Comp. -717,856.58 -293,984.31 3. Materials on Hand 4. Earned Subject to Retention 21,180,900.31 906,875.19 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 23,480,900.31 7. Deductions 8. a.Contract Retentions -1,059,045.02 -45,343.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,421,855.29 861,531.43 10. Reduction Amt to Escrow 11. Payment to Escrow 1,059,040.00 12. Net Pymt. this Estimate 861,531.43