Dept. of Trans. PROGRESS Serial No. Contract No. 11-080-08-31 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 77% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 25 Payment period ending: 03-18-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,143,698.50 39,589.99 2.a. Extra Work 2,119,848.55 325,200.17 b. Adjustment Comp. -705,356.58 12,500.00 3. Materials on Hand 4. Earned Subject to Retention 21,558,190.47 377,290.16 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 23,858,190.47 7. Deductions 8. a.Contract Retentions -1,077,909.52 -18,864.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,780,280.95 358,425.66 10. Reduction Amt to Escrow 11. Payment to Escrow 1,077,900.00 12. Net Pymt. this Estimate 358,425.66