Dept. of Trans. PROGRESS Serial No. Contract No. 11-144-10-24 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 88% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 26 Payment period ending: 05-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,145,117.58 1,419.08 2.a. Extra Work 2,185,137.37 65,288.82 b. Adjustment Comp. -705,356.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,624,898.37 66,707.90 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 23,924,898.37 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -1,081,244.92 -3,335.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,833,653.45 53,372.50 10. Reduction Amt to Escrow 11. Payment to Escrow 1,081,240.00 12. Net Pymt. this Estimate 53,372.50