Dept. of Trans. PROGRESS Serial No. Contract No. 11-202-16-30 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 95% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 28 Payment period ending: 07-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,233,262.58 60,000.00 2.a. Extra Work 2,406,330.70 101,013.61 b. Adjustment Comp. -706,132.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,933,461.14 161,013.61 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 24,233,461.14 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions -1,096,673.06 -8,050.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,131,788.08 157,962.93 10. Reduction Amt to Escrow 11. Payment to Escrow 1,096,670.00 12. Net Pymt. this Estimate 157,962.93