Dept. of Trans. PROGRESS Serial No. Contract No. 03-169-13-59 03-1A46U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 14% 03-SUT-99-22.6/28.6 Federal Project: ACST-P099(444) TP-P099(444) HP21-5918(48) Progress payment No. 03 Payment period ending: 06-20-03 BALDWIN CONTRACTING COMPANY INC 4509 SKYWAY DR MARYSVILLE CA 95901 Escrow No. 02068 Total Estimate This Estimate 1. Contract Itms Without Mobil. 608,162.74 250,221.40 2.a. Extra Work 9,123.09 9,123.09 b. Adjustment Comp. 3. Materials on Hand 6,154.02 6,154.02 4. Earned Subject to Retention 623,439.85 265,498.51 5. Mobilization 12,500.00 12,500.00 6. Total Work Completed 629,785.83 7. Deductions 8. a.Contract Retentions -62,343.99 -26,549.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 573,595.86 251,448.65 10. Reduction Amt to Escrow 11. Payment to Escrow 62,340.00 12. Net Pymt. this Estimate 251,448.65