Dept. of Trans. PROGRESS Serial No. Contract No. 04-169-13-33 03-1A46U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 74% 03-SUT-99-22.6/28.6 Federal Project: ACST-P099(444) TP-P099(444) HP21-5918(48) Progress payment No. 15 Payment period ending: 06-18-04 BALDWIN CONTRACTING COMPANY INC 4509 SKYWAY DR MARYSVILLE CA 95901 Escrow No. 02068 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,714,871.53 503,473.88 2.a. Extra Work 115,898.69 22,557.52 b. Adjustment Comp. 12,532.35 0.00 3. Materials on Hand 14,450.53 -14,626.17 4. Earned Subject to Retention 7,857,753.10 511,405.23 5. Mobilization 25,000.00 0.00 6. Total Work Completed 7,868,302.57 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -392,887.66 -25,570.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,479,865.44 475,834.96 10. Reduction Amt to Escrow 11. Payment to Escrow 392,880.00 12. Net Pymt. this Estimate 475,834.96