Dept. of Trans. PROGRESS Serial No. Contract No. 05-145-11-04 03-1A46U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SUT-99-22.6/28.6 Federal Project: ACST-P099(444) TP-P099(444) HP21-5918(48) Progress payment No. 23 Payment period ending: 05-20-05 BALDWIN CONTRACTING COMPANY INC 4509 SKYWAY DR MARYSVILLE CA 95901 Escrow No. 02068 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,338,211.01 2,040.00 2.a. Extra Work 264,183.75 4,100.89 b. Adjustment Comp. 454,170.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,056,564.76 6,140.89 5. Mobilization 25,000.00 0.00 6. Total Work Completed 13,081,564.76 7. Deductions -17,000.00 0.00 8. a.Contract Retentions -652,828.24 -307.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,411,736.52 5,833.84 10. Reduction Amt to Escrow 11. Payment to Escrow 652,820.00 12. Net Pymt. this Estimate 5,833.84