Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-16-06 03-1A5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 40% 03-NEV-20-0.0/R4.1 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,992,099.81 2,599,533.87 2.a. Extra Work 137,780.97 -20,595.05 b. Adjustment Comp. -47,184.00 0.00 3. Materials on Hand 177,629.33 68,404.19 4. Earned Subject to Retention 15,260,326.11 2,647,343.01 5. Mobilization 3,154,000.00 0.00 6. Total Work Completed 18,236,696.78 7. Deductions -10,000.00 20,000.00 8. a.Contract Retentions -763,016.31 -132,367.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,641,309.80 2,534,975.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,534,975.86