Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-13-13 03-1A5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 45% 03-NEV-20-0.0/R4.1 Federal Project: NONE Progress payment No. 11 Payment period ending: 09-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,862,022.12 2,869,922.31 2.a. Extra Work 245,752.77 42,899.09 b. Adjustment Comp. -47,184.00 0.00 3. Materials on Hand 153,179.08 -24,450.25 4. Earned Subject to Retention 18,213,769.97 2,888,371.15 5. Mobilization 3,320,000.00 166,000.00 6. Total Work Completed 21,380,590.89 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -910,688.50 -144,418.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,613,081.47 2,909,952.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,909,952.59