Dept. of Trans. PROGRESS Serial No. Contract No. 07-296-11-57 03-1A5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 50% 03-NEV-20-0.0/R4.1 Federal Project: NONE Progress payment No. 13 Payment period ending: 10-19-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,603,466.66 2,255,170.48 2.a. Extra Work 274,800.16 29,047.39 b. Adjustment Comp. -47,184.00 0.00 3. Materials on Hand 106,838.06 -46,341.02 4. Earned Subject to Retention 20,937,920.88 2,237,876.85 5. Mobilization 3,320,000.00 0.00 6. Total Work Completed 24,151,082.82 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions -1,046,896.04 -111,893.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,196,024.84 2,120,983.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,120,983.01