Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-301-10-56 03-1A5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-20-0.0/R4.1 Federal Project: NONE Progress payment No. 25 Payment period ending: 08-29-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,880,413.07 50,755.46 2.a. Extra Work 820,156.65 51,324.45 b. Adjustment Comp. 276,607.67 -461.83 3. Materials on Hand 4. Earned Subject to Retention 31,977,177.39 101,618.08 5. Mobilization 3,320,000.00 0.00 6. Total Work Completed 35,297,177.39 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -1,577,564.47 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,577,564.47 0.00 9. Total pay to Contractor 35,287,177.39 101,618.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,618.08