Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-08-45 03-1A7314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 24% 03-ED-50-67.6/72.9 Federal Project: NH-P050(131) Progress payment No. 03 Payment period ending: 05-21-14 DON GARCIA EXCAVATING AND PAVING INC P O BOX 7176 SOUTH LAKE TAHOE, CA 96158 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 596,552.50 324,342.50 2.a. Extra Work 44,647.69 10,712.18 b. Adjustment Comp. 3. Materials on Hand 46,592.84 46,592.84 4. Earned Subject to Retention 687,793.03 381,647.52 5. Mobilization 168,000.00 56,000.00 6. Total Work Completed 809,200.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 855,793.03 437,647.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 437,647.52