Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-352-09-41 03-1A7314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-67.6/72.9 Federal Project: NH-P050(131) Progress payment No. 10 Payment period ending: 10-31-14 DON GARCIA EXCAVATING AND PAVING INC P O BOX 7176 SOUTH LAKE TAHOE, CA 96158 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,000,678.16 294,664.28 2.a. Extra Work 845,600.92 334,029.32 b. Adjustment Comp. -4,260.30 -13,607.00 3. Materials on Hand 4. Earned Subject to Retention 5,842,018.78 615,086.60 5. Mobilization 224,000.00 0.00 6. Total Work Completed 6,066,018.78 7. Deductions -30,000.00 -15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,036,018.78 600,086.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 600,086.60