Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-033-13-58 03-1A7314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-67.6/72.9 Federal Project: NH-P050(131) Progress payment No. 11 Payment period ending: 10-31-14 DON GARCIA EXCAVATING AND PAVING INC P O BOX 7176 SOUTH LAKE TAHOE, CA 96158 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,157,742.16 157,064.00 2.a. Extra Work 867,723.28 22,122.36 b. Adjustment Comp. -4,260.30 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,021,205.14 179,186.36 5. Mobilization 224,000.00 0.00 6. Total Work Completed 6,245,205.14 7. Deductions -10,000.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,235,205.14 199,186.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 199,186.36