Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-11-23 03-1A73U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 55% 03-ED-50-77.3/79.3 Federal Project: NH Progress payment No. 33 Payment period ending: 10-17-13 DISNEY CONSTRUCTION INC 859 COWAN ROAD STE 3 BURLINGAME CA 94513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,015,872.56 61,621.50 2.a. Extra Work 1,858,059.18 201,206.16 b. Adjustment Comp. 1,008,669.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,882,600.96 262,827.66 5. Mobilization 1,080,000.00 0.00 6. Total Work Completed 15,962,600.96 7. Deductions -82,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,880,600.96 257,827.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,827.66