Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-197-10-36 03-1A73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-50-77.3/79.3 NH Progress payment No. 049 Payment period ending: 10-10-14 DISNEY CONSTRUCTION INC 859 COWAN ROAD STE 3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,312,940.56 4,000.00 2. a. Extra Work 2,350,773.42 21,281.00 b. Adustment Comp. 4,020,514.93 2,027,927.00 3. Materials on Hand 4. Earned Subject to Retention 18,684,228.91 2,053,208.00 5. Mobilization 1,080,000.00 0.00 6. Total Work Completed 19,764,228.91 7. Deductions -249.90 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,763,979.01 2,063,208.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,063,208.00