Dept. of Trans. PROGRESS Serial No. Contract No. 04-328-09-36 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 32% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 05 Payment period ending: 11-19-04 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,092,192.99 630,454.90 2.a. Extra Work 16,849.50 0.00 b. Adjustment Comp. -8,950.00 -13,200.00 3. Materials on Hand 335,049.66 -4,942.52 4. Earned Subject to Retention 3,435,142.15 612,312.38 5. Mobilization 2,400,000.00 800,000.00 6. Total Work Completed 5,500,092.49 7. Deductions -30,520.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,804,622.15 1,402,312.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,402,312.38