Dept. of Trans. PROGRESS Serial No. Contract No. 04-357-10-35 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 32% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 06 Payment period ending: 12-20-04 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,358,444.69 266,251.70 2.a. Extra Work 149,074.21 132,224.71 b. Adjustment Comp. -8,950.00 0.00 3. Materials on Hand 752,381.26 417,331.60 4. Earned Subject to Retention 4,250,950.16 815,808.01 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 5,898,568.90 7. Deductions -10,520.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,640,430.16 835,808.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 835,808.01