Dept. of Trans. PROGRESS Serial No. Contract No. 05-054-16-35 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 32% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 08 Payment period ending: 02-18-05 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,358,444.69 0.00 2.a. Extra Work 330,096.49 56,129.94 b. Adjustment Comp. -8,950.00 0.00 3. Materials on Hand 1,575,299.66 805,490.41 4. Earned Subject to Retention 5,254,890.84 861,620.35 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 6,079,591.18 7. Deductions -18,520.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,636,370.84 858,620.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 858,620.35