Dept. of Trans. PROGRESS Serial No. Contract No. 05-083-16-08 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 32% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 09 Payment period ending: 03-18-05 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,606,834.69 248,390.00 2.a. Extra Work 332,359.50 2,263.01 b. Adjustment Comp. -8,950.00 0.00 3. Materials on Hand 1,576,908.00 1,608.34 4. Earned Subject to Retention 5,507,152.19 252,261.35 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 6,330,244.19 7. Deductions -19,520.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,887,632.19 251,261.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 251,261.35