Dept. of Trans. PROGRESS Serial No. Contract No. 05-172-14-26 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 45% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 12 Payment period ending: 06-20-05 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,744,410.06 2,375,078.64 2.a. Extra Work 415,407.04 69,928.64 b. Adjustment Comp. -61,933.21 -42,522.30 3. Materials on Hand 1,739,083.63 -172,955.66 4. Earned Subject to Retention 9,836,967.52 2,229,529.32 5. Mobilization 3,040,000.00 0.00 6. Total Work Completed 11,137,883.89 7. Deductions -12,780.00 1,260.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,864,187.52 2,230,789.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,230,789.32