Dept. of Trans. PROGRESS Serial No. Contract No. 05-269-14-33 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 67% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 18 Payment period ending: 09-20-05 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,595,624.80 5,433,243.07 2.a. Extra Work 667,009.63 41,203.80 b. Adjustment Comp. 187,344.11 4,246.48 3. Materials on Hand 616,688.20 -348,971.80 4. Earned Subject to Retention 24,066,666.74 5,129,721.55 5. Mobilization 3,200,000.00 0.00 6. Total Work Completed 26,649,978.54 7. Deductions -65,290.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,201,376.74 5,119,721.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,119,721.55