Dept. of Trans. PROGRESS Serial No. Contract No. 06-115-10-08 03-1A8014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 81% 03-PLA-80-39.0/R55.7 Federal Project: ACIM-080-4(175) ACIM-080-4(175) Progress payment No. 26 Payment period ending: 04-20-06 BROSAMER GRANITE A JOINT VENTURE P O BOX 238 ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,493,543.41 285.00 2.a. Extra Work 1,162,845.94 41,980.78 b. Adjustment Comp. 491,746.44 -35,053.89 3. Materials on Hand 22,259.71 0.00 4. Earned Subject to Retention 31,170,395.50 7,211.89 5. Mobilization 3,200,000.00 0.00 6. Total Work Completed 34,348,135.79 7. Deductions -199,054.52 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,171,340.98 1,211.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,211.89