Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-100-16-11 03-1A8414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-89-0.0/8.6 Federal Project: SARR-P089(94) A-P089(94) Progress payment No. 27 Payment period ending: 01-12-12 QUALCON CONTRACTORS INC 1645 ESMERALDA AVENUE MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,712,195.58 7,975.00 2.a. Extra Work 434,365.50 7,820.21 b. Adjustment Comp. 785,632.74 280,440.83 3. Materials on Hand 4. Earned Subject to Retention 11,932,193.82 296,236.04 5. Mobilization 650,000.00 0.00 6. Total Work Completed 12,582,193.82 7. Deductions -10,000.00 30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,572,193.82 326,236.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 326,236.04