Dept. of Trans. PROGRESS Serial No. Contract No. 16-301-08-45 03-1A8434 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 64% Location: Federal Project: 03-ED-89-13.8/18.0 STP-P089(112) Progress payment No. 007 Payment period ending: 10-20-16 DON GARCIA EXCAVATING & PAVING INC PO BOX 7176 SO LAKE TAHOE CA 96158 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,440,721.99 1,845,092.08 2. a. Extra Work 209,414.59 30,427.00 b. Adustment Comp. 7,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,657,136.58 1,875,519.08 5. Mobilization 800,000.00 0.00 6. Total Work Completed 7,457,136.58 7. Deductions -1,937.10 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,455,199.48 1,875,519.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,875,519.08