Dept. of Trans. PROGRESS Serial No. Contract No. 15-233-09-21 03-1A8444 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 68% Location: Federal Project: 03-ED-89-18.0/24.9 ACST-P089(105) P-P089(105) Progress payment No. 014 Payment period ending: 08-20-15 DIABLO CONTRACTORS INC 7 CROW CANYON COURT, SUITE 10 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,857,036.79 595,151.25 2. a. Extra Work 558,552.77 22,689.81 b. Adustment Comp. 38,230.89 -28.64 3. Materials on Hand 40,000.00 0.00 4. Earned Subject to Retention 7,493,820.45 617,812.42 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 8,553,820.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,593,820.45 617,812.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 617,812.42