Dept. of Trans. PROGRESS Serial No. Contract No. 20-210-09-27 03-1A9204 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 57% Location: Federal Project: 03-SUT-20-5.0/11.3 B1NH-P020(184) Progress payment No. 012 Payment period ending: 07-20-20 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,665,686.96 3,184,828.29 2. a. Extra Work 266,221.74 167,624.42 b. Adustment Comp. 49,503.88 0.00 3. Materials on Hand 33,208.55 33,208.55 4. Earned Subject to Retention 10,014,621.13 3,385,661.26 5. Mobilization 1,425,000.00 0.00 6. Total Work Completed 11,406,412.58 7. Deductions -12,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,427,621.13 3,375,661.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,375,661.26