Dept. of Trans. PROGRESS Serial No. Contract No. 05-268-13-57 03-1A9304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 74% 03-YOL-80-6.4/R11.3 Federal Project: ACIM-080-2(344) Progress payment No. 05 Payment period ending: 09-20-05 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,524,911.13 1,073,056.93 2.a. Extra Work b. Adjustment Comp. -54,896.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,470,014.59 1,073,056.93 5. Mobilization 770,000.00 38,500.00 6. Total Work Completed 5,240,014.59 7. Deductions -500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,239,514.59 1,111,556.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,111,556.93