Dept. of Trans. PROGRESS Serial No. Contract No. 05-300-11-11 03-1A9304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 93% 03-YOL-80-6.4/R11.3 Federal Project: ACIM-080-2(344) Progress payment No. 06 Payment period ending: 10-20-05 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,291,906.26 766,995.13 2.a. Extra Work b. Adjustment Comp. -54,896.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,237,009.72 766,995.13 5. Mobilization 770,000.00 0.00 6. Total Work Completed 6,007,009.72 7. Deductions -8,560.00 -8,060.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,998,449.72 758,935.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 758,935.13