Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-340-10-58 03-1A9304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-YOL-80-6.4/R11.3 Federal Project: ACIM-080-2(344) Progress payment No. 07 Payment period ending: 11-16-05 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,489,245.56 197,339.30 2.a. Extra Work b. Adjustment Comp. -28,719.58 26,176.96 3. Materials on Hand 4. Earned Subject to Retention 5,460,525.98 223,516.26 5. Mobilization 770,000.00 0.00 6. Total Work Completed 6,230,525.98 7. Deductions -33,560.00 -25,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,196,965.98 198,516.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 198,516.26