Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-14-42 03-1A97W4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 43% 03-COL-20-33.1/R39.4 Federal Project: ACNH-P020(143) Progress payment No. 06 Payment period ending: 09-20-07 TEICHERT CONSTRUCTION P O BOX 1890 DAVIS CA 956171890 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,243,598.49 3,157,984.22 2.a. Extra Work 163,152.62 160,490.05 b. Adjustment Comp. 98,901.42 98,901.42 3. Materials on Hand 4. Earned Subject to Retention 11,505,652.53 3,417,375.69 5. Mobilization 630,000.00 0.00 6. Total Work Completed 12,135,652.53 7. Deductions -4,000.00 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,131,652.53 3,419,375.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,419,375.69