Dept. of Trans. PROGRESS Serial No. Contract No. 08-357-15-46 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 72% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 06 Payment period ending: 12-19-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,784,932.66 334,006.56 2.a. Extra Work 51,278.25 23,240.33 b. Adjustment Comp. -10,534.91 0.00 3. Materials on Hand 34,794.07 0.00 4. Earned Subject to Retention 2,860,470.07 357,246.89 5. Mobilization 500,000.00 25,000.00 6. Total Work Completed 3,325,676.00 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,345,470.07 377,246.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,246.89