Dept. of Trans. PROGRESS Serial No. Contract No. 09-021-14-29 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 83% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 07 Payment period ending: 01-20-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,940,959.50 156,026.84 2.a. Extra Work 51,278.25 0.00 b. Adjustment Comp. -6,153.86 4,381.05 3. Materials on Hand 34,794.07 0.00 4. Earned Subject to Retention 3,020,877.96 160,407.89 5. Mobilization 500,000.00 0.00 6. Total Work Completed 3,486,083.89 7. Deductions -21,338.32 -6,338.32 8. a.Contract Retentions b. Unsatisfactory Prog. -16,040.79 -16,040.79 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,483,498.85 138,028.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,028.78