Dept. of Trans. PROGRESS Serial No. Contract No. 09-054-13-42 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 86% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 08 Payment period ending: 02-20-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,032,399.50 91,440.00 2.a. Extra Work 52,048.60 770.35 b. Adjustment Comp. -6,153.86 0.00 3. Materials on Hand 34,794.07 0.00 4. Earned Subject to Retention 3,113,088.31 92,210.35 5. Mobilization 500,000.00 0.00 6. Total Work Completed 3,578,294.24 7. Deductions -27,338.32 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 16,040.79 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,585,749.99 102,251.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,251.14