Dept. of Trans. PROGRESS Serial No. Contract No. 09-082-16-30 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 86% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 09 Payment period ending: 03-20-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,032,639.50 240.00 2.a. Extra Work 53,698.60 1,650.00 b. Adjustment Comp. -2,343.61 3,810.25 3. Materials on Hand 121,800.00 87,005.93 4. Earned Subject to Retention 3,205,794.49 92,706.18 5. Mobilization 500,000.00 0.00 6. Total Work Completed 3,583,994.49 7. Deductions -38,338.32 -11,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,667,456.17 81,706.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,706.18