Dept. of Trans. PROGRESS Serial No. Contract No. 09-168-13-35 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 11 Payment period ending: 06-19-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,891,416.03 284,814.36 2.a. Extra Work 251,616.19 177,473.26 b. Adjustment Comp. -90,978.29 -5,502.01 3. Materials on Hand 4. Earned Subject to Retention 5,052,053.93 456,785.61 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,552,053.93 7. Deductions -21,848.32 25,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,530,205.61 481,785.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 481,785.61