Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-174-11-28 03-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 03-COL-20-2.9/3.7 Federal Project: ACNH-P020(148) ACBR-P020(148) NH-P020(148) Progress payment No. 12 Payment period ending: 06-19-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,995,510.03 104,094.00 2.a. Extra Work 252,196.78 580.59 b. Adjustment Comp. -90,630.60 347.69 3. Materials on Hand 4. Earned Subject to Retention 5,157,076.21 105,022.28 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,657,076.21 7. Deductions -21,848.32 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,635,227.89 105,022.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,022.28