Dept. of Trans. PROGRESS Serial No. Contract No. 12-325-11-23 03-1E0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 88% 03-PLA-89-13.7/21.7 Federal Project: ACST-P089(103) P Progress payment No. 05 Payment period ending: 11-20-12 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,359,042.17 224,368.70 2.a. Extra Work 119,067.83 47,391.98 b. Adjustment Comp. -83,879.79 64,488.57 3. Materials on Hand 4. Earned Subject to Retention 6,394,230.21 336,249.25 5. Mobilization 600,000.00 0.00 6. Total Work Completed 6,994,230.21 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,992,230.21 336,249.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 336,249.25