Dept. of Trans. PROGRESS Serial No. Contract No. 10-144-15-34 03-1E0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 9% 03-COL-20-R21.5/R22.4 Federal Project: SARR-P020(150) A-P020(150) Progress payment No. 04 Payment period ending: 05-20-10 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,609.50 167,609.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 925,816.62 -57,984.00 4. Earned Subject to Retention 1,093,426.12 109,625.50 5. Mobilization 147,250.00 31,000.00 6. Total Work Completed 314,859.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,240,676.12 140,625.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,625.50