Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-13-52 03-1E0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 45% 03-COL-20-R21.5/R22.4 Federal Project: SARR-P020(150) A-P020(150) Progress payment No. 06 Payment period ending: 07-20-10 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,212,909.40 1,548,358.85 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 62,397.25 -117,175.70 4. Earned Subject to Retention 3,275,306.65 1,431,183.15 5. Mobilization 155,000.00 7,750.00 6. Total Work Completed 3,367,909.40 7. Deductions -205,000.00 -205,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,225,306.65 1,233,933.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,233,933.15